CA0-001 Exam Topic 7 Question 62 Discussion:
Question #: 62
Topic #: 7

You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?


A.

$-00,000


B.

$200,00


C.

$50,000


D.

None of the above