New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 73 Topic 8 Discussion

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 73 Topic 8 Discussion

CA0-001 Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?


A.

Parametric estimating


B.

Funding limit reconciliation


C.

Reserves analysis


D.

None of the above


Get Premium CA0-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.