PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 22 Topic 3 Discussion

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 22 Topic 3 Discussion

CA0-001 Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

Which of the following is NOT an example of a type of schedule report?


A.

Gantt chart


B.

Milestone chart


C.

fishbone diagram


D.

network diagram