Question #: 23
Topic #: 3

Which type of network diagram allows you to depict four types of dependencies (finish-to-start, finish-to-finish, start-to-start, and start-to-finish)?


A.

Precedence Diagramming Method (PDM)


B.

Gant Cnart Diagram (GCD)


C.

Dependency Diagramming Method (DDM)


D.

Arrow Diagramming Method (ADM)