CA0-001 Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

Define Scope involves subdividing the major project deliverables into smaller, more manageable components to __________.


A.

Improve the accuracy of cost, time and resource estimates


B.

Define a baseline for performance measurement and control


C.

Facilitate clear responsibility assignments


D.

Al1 of the above