New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 25 Topic 3 Discussion

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 25 Topic 3 Discussion

CA0-001 Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

Which process must occur after a project manager has been assigned to the project?


A.

Collect Requirements


B.

Develop the project charter


C.

Develop the project statement of work


D.

Develop project closing document


Get Premium CA0-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.