CA0-001 Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

Which process must occur after a project manager has been assigned to the project?


A.

Collect Requirements


B.

Develop the project charter


C.

Develop the project statement of work


D.

Develop project closing document