PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 31 Topic 4 Discussion

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 31 Topic 4 Discussion

CA0-001 Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

You are the project manager of a project .You have just completed the Define Activities, activity resources estimating, and Estimate Activity Durations processes. Which process have you left out?


A.

Control Schedule


B.

Create WBS


C.

Sequence Activities


D.

Operations


Get Premium CA0-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.