PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 37 Topic 4 Discussion

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 37 Topic 4 Discussion

CA0-001 Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :


A.

Start-to-Finish


B.

Finish-to-Start


C.

Start-to-Start


D.

Finish-to-Finish