CA0-001 Exam Topic 4 Question 34 Discussion:
Question #: 34
Topic #: 4

The planning processes are:


A.

Define Scope, Resource planning, Estimate Costs, Schedule development. Define Activities


B.

Inputs, Control, Status reports, Risk management


C.

Planning, Resource planning, Quality assurance, Risk control


D.

Define Scope, Team development, Control Schedule, Budget control, Contract administration