PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 34 Topic 4 Discussion

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 34 Topic 4 Discussion

CA0-001 Exam Topic 4 Question 34 Discussion:
Question #: 34
Topic #: 4

The planning processes are:


A.

Define Scope, Resource planning, Estimate Costs, Schedule development. Define Activities


B.

Inputs, Control, Status reports, Risk management


C.

Planning, Resource planning, Quality assurance, Risk control


D.

Define Scope, Team development, Control Schedule, Budget control, Contract administration


Get Premium CA0-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.