CA0-001 Exam Topic 4 Question 35 Discussion:
Question #: 35
Topic #: 4

A Reserve Analysis is a technique for:


A.

Estimate Activity Durations


B.

Estimate Activity Resources


C.

Sequence Activities


D.

Define Activities