Major renovation projects must meet which of the following minimum percentage savings when taking credit for renewable energy systems?
What are the Storage and Collection of Recyclables requirements for only Retail projects under the Materials and Resources Prerequisite?
The project team is working to reduce the building's total energy costs in a cold climate. Which is the best strategy for the project team to consider?
The project landscape architect suggests reducing the area planned for surface parking and replacing it with additional vegetated space. What benefit would this strategy provide to the owner?
The Sustainable Sites Credit, Heat Island Reduction takes into account both new and three-year aged Solar Reflectance Index (SRI) values for roofing material because
Which of the following is omitted from the assessment while performing preliminary energy modeling?
The project team wants to modify the design of an office building copy room to minimize the risk of airborne contamination to the surrounding space. The design includes a separate exhaust, but due to design constraints the partition walls of the room cannot run deck-to-deck. What can the team do to achieve Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies?
The material cost for a project is $100,000. What is the minimum material value needed to achieve Materials and Resources Credit, Building Disclosure and Optimization, Sourcing of Raw Materials, Option 2. Leadership Extraction
Practices?
Selecting a high-reflectance interior paint which is compliant with South Coast Air Quality Management District (SCAQMD) Rule 1113 can help contribute towards which two credits?
Which of the following are all considered regular building occupants?