Questions # 21:

In order to meet the minimum qualifications for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification a Commissioning (Cx) agent must have completed the commissioning process activities for a minimum of how many similar projects?

Options:

A.

Zero


B.

One


C.

Two


D.

Three


Expert Solution
Questions # 22:

Under Energy and Atmosphere Credit: Optimize Energy Performance, Option 1: Whole-Building Energy Simulation, how can the energy cost savings be accurately determined?


Expert Solution
Questions # 23:

In order to achieve the requirements of LEED, the Electrical Vehicle Supply Equipment (EVSE) must comply with:

Options:

A.

State, but not regional standards established for electrical vehicles operated within the state of vehicle operation


B.

Regional, state, or local standards for the electrical connectors to be used


C.

Level 1 charging capacity (110 volts AC)


D.

Manufacturer's standards established for electrical vehicles operated within the state of vehicle primary operation


Expert Solution
Questions # 24:

What percentage of all energy usage is attributable to buildings?

Options:

A.

60%


B.

30%


C.

40%


D.

50%


Expert Solution
Questions # 25:

In addition to Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 3. Building and Materials Reuse, salvaged materials contribute to the achievement of

Options:

A.

Materials and Resources Prerequisite, Storage and Collection of Recyclables


B.

Materials and Resources Credit, Building Product Disclosure and Optimization - Material Ingredients


C.

Materials and Resources Credit, Construction and Demolition Waste Management


D.

Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations


Expert Solution
Questions # 26:

Which of the following buildings meets the Minimum Program Requirements for LEED certification?

Options:

A.

A 1,500 ft2 (139 m2) Tourism Center located on a previously undeveloped one-acre site


B.

A 20,000 ft2 (1 859 m2) Transit Parking Garage located on a previously developed five-acre site


C.

A 2,500 ft2 (232 m2) mobile Health Clinic located on a previously constructed above-water dock


D.

A 5,000 ft2 (465 m2) Science Education center on an above-water pier that is being built specifically for the Education center


Expert Solution
Questions # 27:

What type of lighting can be used for 25% or less of the total connected lighting load for all regularly occupied spaces as a strategy to improve lighting quality?

Options:

A.

Low-mercury lighting


B.

Direct-only overhead lighting


C.

Light sources with a CRI of 80 or higher


D.

Low fixture glare


Expert Solution
Questions # 28:

A new five-story building with a 30,000 ft2 (2 800 m2) footprint is being designed on a previously disturbed100,000 ft2 (9 290 m2) site. The remaining on-grade surface will be 35,000 ft2 (3 250 m2) of asphalt parking, and 35,000 ft2 (3 250 m2) of native vegetated open space. To achieve a point for exemplary performance under Option 1 of Sustainable Sites Credit, Site Development - Protect or Restore Habitat, the design team will have to incorporate a native and/or adapted vegetated roof with a minimum area of

Options:

A.

12,500 ft2 (1 160 m2)


B.

15,000 ft2 (1 400 m2)


C.

25,000 ft2 (2 300 m2)


D.

35,000 ft2 (3 250 m2)


Expert Solution
Questions # 29:

A community center will be built on a plot in two phases. Phase 1 will include the building with a pool and gymnasium, while Phase 2 will include the outdoor grass soccer fields. For Phase 1 to achieve certification, where can the project set the LEED boundary?

Options:

A.

Around Phase 1 and 2


B.

Around Phase 1 and 2 while committing to keep the Phase 2 grounds undisturbed


C.

Around Phase 1


D.

Around Phase 1 while committing to keep the Phase 2 grounds undisturbed


Expert Solution
Questions # 30:

An accessible garden planted with native plants contributes to the achievement of which of the following credit pairs?

Options:

A.

Sustainable Sites Credit, Sensitive Land Protection; Sustainable Sites Credit, Site Development - Protect or Restore Habitat


B.

Sustainable Sites Credit, Open Space; Sustainable Sites Credit, Rainwater Management


C.

Water Efficiency Credit, Water Metering; Sustainable Sites Credit, Tenant Design and Construction Guidelines


D.

Location and Transportation Credit, Surrounding Density and Diverse Uses; Sustainable Sites Credit, Site Assessment