Questions # 71:

Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have the tools and environment to completely finish each selected Product Backlog item? (choose the best two answers)

Options:

A.

Declare the Scrum Team not ready for Scrum.


B.

Coach the Scrum Team to improve its skills, tools and environment over time and adjust the Definition of Done accordingly.


C.

Encourage the Product Owner to accept partially done Increments until the

situation improves.


D.

Refocus the current Sprint on establishing the Scrum Team ' s environment instead of delivering an Increment.


E.

Have the Scrum Team establish a Definition of Done that is actually possible to achieve given current circumstances.


Expert Solution
Questions # 72:

(Which of the following activities will a Product Owner engage in during a Sprint?

Choose the best answer.)

Options:

A.

Answer questions from the Developers about items in the current Sprint.


B.

Prioritize the Developers’ work on the Sprint Backlog.


C.

Run the Daily Scrum.


D.

Update management on what is being worked on.


Expert Solution
Questions # 73:

What does it mean to say that an event has a time-box?

Options:

A.

The event must happen at a set time.


B.

The event must happen by a given time.


C.

The event must take at least a minimum amount of time.


D.

The event can take no more than a maximum amount of time.


Expert Solution
Questions # 74:

What are three ways Scrum promotes self-management?

Options:

A.

By having the Scrum Master protect the Scrum Team.


B.

By the Scrum Team deciding what work to do in a Sprint.


C.

By being a lightweight framework.


D.

By removing titles for Scrum Team members.


Expert Solution
Questions # 75:

Who should know the most about the progress toward a business objective or a release?

Options:

A.

The Project Manager.


B.

The Scrum Master.


C.

The Development Team.


D.

The Product Owner.


Expert Solution
Questions # 76:

The Product Owner determines how many Product Backlog items the Development Team selects for a Sprint.

Options:

A.

False.


B.

True, accordingly to what was committed to the stakeholders.


C.

True, but only after confirmation by the resource manager that the Team has enough capacity.


D.

True.


E.

False, the Scrum Master does that.


F.

False, capacity and commitment are the Project manager’s responsibility.


Expert Solution
Questions # 77:

Which statement best describes Scrum?

Options:

A.

A defined and predictive process that confirms to the principles of Scientific Management.


B.

A complete methodology that defines how to develop software.


C.

A cookbook that defines best practices for software development.


D.

A framework within which complex products in complex environments are developed.


Expert Solution
Questions # 78:

The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?

Options:

A.

Add the item to the current Sprint and drop an item of equal size.


B.

Add the item to the current Sprint without any adjustments.


C.

Inform the Product Owner so he/she can work with the CEO.


D.

Add the item to the next Sprint.


Expert Solution
Questions # 79:

You have six teams using a traditional method to deliver a product. Your management has asked you to start using Scrum. In the initial project there were separate plans and teams for the layers of a software system, i.e. one for the front-end, one for the middle tier, one for the back-end, and one for the interfaces and services. This resembles what is known as component teams. But you have read that it’s a good idea to have teams organized by feature.

What are the advantages of keeping component teams while starting Scrum?

Options:

A.

There’s less initial disruption than organizing into new teams. As they start, they will discover what works best, and how to potentially re-organize towards this.


B.

Component teams generally have the skills needed to create a working Increment of software that provides business value.


C.

Because they have worked together for some time, they are likely able to start producing shippable Increments faster that new feature teams would.


D.

There are fewer cross-team dependencies than working in feature teams.


Expert Solution
Questions # 80:

Which of the following is an accountability of a Tester on a Scrum Team?

(choose the best answer)

Options:

A.

Executing tests, finding defects, and reporting them to the Developers.


B.

Refreshing and communicating the Definition of Done to the Product Owner.


C.

Scrum has no Tester accountability. The Developers are accountable for quality.


D.

Verifying the work of the Developers.


E.

Tracking defect rates to ensure they improve each Sprint.