Scrum Professional Scrum Master I PSM-I Question # 72 Topic 8 Discussion

Scrum Professional Scrum Master I PSM-I Question # 72 Topic 8 Discussion

PSM-I Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

(Which of the following activities will a Product Owner engage in during a Sprint?

Choose the best answer.)


A.

Answer questions from the Developers about items in the current Sprint.


B.

Prioritize the Developers’ work on the Sprint Backlog.


C.

Run the Daily Scrum.


D.

Update management on what is being worked on.