Questions # 21:

Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)

Options:

A.

Release Planning.


B.

Release Retrospective.


C.

Sprint Retrospective.


D.

Sprint Planning.


E.

Sprint Testing.


F.

Sprint 0.


G.

Daily Scrum.


Expert Solution
Questions # 22:

When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?

(choose the best answer)

Options:

A.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.


B.

The Scrum Masters from each Scrum Team define a common Definition of Done.


C.

When multiple Scrum Teams are working together on a product, they must mutually define and comply with the same Definition Of Done.


D.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.


Expert Solution
Questions # 23:

Which two things should the Development Team do during the first Sprint? (Choose two.)

Options:

A.

Make up a plan for the rest of the project.


B.

Analyze, describe, and document the requirements for the subsequent Sprints.


C.

Develop at least one piece of functionality.


D.

Analyze, design, and describe the complete architecture and infrastructure.


E.

Create an increment of potentially releasable software.


Expert Solution
Questions # 24:

A Scrum Team is a cohesive unit of professionals that consists of which of the following? (Choose all that

apply.)

Options:

A.

Users.


B.

One Scrum Master.


C.

Developers.


D.

Customers.


E.

One Product Owner.


Expert Solution
Questions # 25:

The time-box for a Daily Scrum?

Options:

A.

Two minutes per person.


B.

15 minutes.


C.

15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.


D.

4 hours.


E.

The same time of day every day.


Expert Solution
Questions # 26:

How should a Development Team deal with non-functional requirements?

Options:

A.

Ensure every Increment meets them.


B.

Make sure the release department understands these requirements, but it is not the Development Team’s responsibility.


C.

Handle them during the Integration Sprint preceding the Release Sprint.


D.

Assign them to the lead developers on the team.


Expert Solution
Questions # 27:

Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)

Options:

A.

Identifying high priority process improvements for the next Sprint.


B.

The order of items in the Product Backlog.


C.

How the team collaborates.


D.

Documenting acceptance criteria for items in the next Sprint.


Expert Solution
Questions # 28:

You have just been hired by a company new to Scrum. Your management has assigned you to

be the Scrum Master of six new Scrum Teams. These teams will build one product Select two

conditions you should strive tor in this scenario.

(choose the best two answers)

Options:

A.

There should be six Product Owners, one tor each Scrum Team.


B.

There should be six Product Owners, reporting to a Chief Product Owner.


C.

The product has one Product Backlog.


D.

Each Scrum Team should have a separate Product Backlog.


E.

There should be only one Product Owner.


Expert Solution
Questions # 29:

(What are the two primary ways a Scrum Master helps a Scrum Team work at its highest level of productivity?

Choose the best two answers.)

Options:

A.

By keeping high-value features high in the Product Backlog.


B.

By facilitating Scrum Team decisions.


C.

By ensuring the meetings start and end at the proper time.


D.

By removing impediments that hinder the Scrum Team.


Expert Solution
Questions # 30:

How much work Is required of the Developers to complete a Product Backlog Item selected during the Sprint Planning?

(choose the best answer)

Options:

A.

All development work and at least some testing.


B.

as much as is required to meet the Scrum Team ' s Definition of Done.


C.

A proportional amount of time on analysis, design development and testing


D.

As much as they can fit into the Sprint, with remaining work deferred to the next Sprint


Expert Solution