Question #: 77
Topic #: 8

When multiple Scrum Teams are working on the same product, should all of their Increments be

integrated every Sprint? (choose the best answer)


A.

Yes, but only for Scrum Teams whose work has dependencies.


B.

No, that is tar too nard and must be done in a hardening Sprint


C.

No, each Scrum Team stands alone.


D.

Yes, in order to accurately inspect what is done.