The correct answer is A, because the Product Owner does not determine how many Product Backlog items the Development Team selects for a Sprint. The Scrum Guide states that “the number of items selected from the Product Backlog for the Sprint is solely up to the Development Team. Only the Development Team can assess what it can accomplish over the upcoming Sprint.” Therefore, the Development Team is responsible for choosing the scope of work for a Sprint.