What enhances the transparency of an increment?


A.

Doing all work needed to meet the definition of “Done”


B.

Reporting Sprint progress to the stakeholders daily


C.

Keeping track of and estimating all undone work to be completed in a separate Sprint.


D.

Updating Sprint tasks properly in the electronic tracking tool.