Questions # 41:

What is a strategy a Product Owner can use during Program Increment Planning to mini-mize dependencies?

Options:

A.

Change the definition of done


B.

Move Stories on their team's backlog to another team


C.

Reprioritize Epics


Expert Solution
Questions # 42:

The Release Train Engineer ensures that Business Owners assign business value to what during Program Increment (PI) Planning?

Options:

A.

Program-level PI Objectives


B.

Stories


C.

Features


D.

Team-level PI Objectives


Expert Solution
Questions # 43:

A team is consistently meeting 100% of their PI Objectives. How should the Release Train Engineer

(RTE) respond?

Options:

A.

Coach the team on their tendency to size Stories too small


B.

Praise the team for being high performers


C.

Praise the team for being a cross-functional team


D.

Coach the team on their tendency to under-commit


Expert Solution
Questions # 44:

What is one technique for building a one-team culture across the ART?

Options:

A.

Ensure the team leader does not show vulnerability


B.

Rotate team members to new teams to facilitate relationship building


C.

Foster an environment in which the whole ART succeeds and fails together


D.

Review each teams' predictability measure with the ART


Expert Solution
Questions # 45:

Which action describes the behavior of applying Systems Thinking for a Release Train Engineer (RTE)?

Options:

A.

Encourages the team to express opinions in all circumstances


B.

Examines what may be missing to make the environment better for the team


C.

Demonstrates appreciation to team members in many ways


D.

Facilitates individual decision-making over team-level decision-making


Expert Solution
Questions # 46:

What is the recommended duration of an Iteration in SAFe?

Options:

A.

Three weeks


B.

Two weeks


C.

Four weeks


D.

Six weeks


Expert Solution
Questions # 47:

What is one primary responsibility of a Release Train Engineer?

Options:

A.

Eliminate impediments


B.

Support the Product Owner


C.

Manage and optimize the Release on Demand process


D.

Manage and optimize the flow of value through the Agile Release Train


Expert Solution
Questions # 48:

Which three topics are covered on the first day of the Program Increment (PI) Planning event? (Choose three.)

Options:

A.

Ishikawa diagrams


B.

Team velocity Metrics


C.

Business context


D.

Cumulative flow diagrams


E.

Product/Solution Vision


F.

Architecture Vision and development practices


Expert Solution
Questions # 49:

Which of the following is true about the ART sync event?

Options:

A.

It is run after PO-sync and Scrum of Scrum events


B.

It is a combination of PO-sync and Scrum of Scrums events


C.

It occurs during the Innovation and Planning iteration


D.

Attendance by the entire ART is important


Expert Solution
Questions # 50:

What should the Release Train Engineer do during the final plan review on Day two of Program Increment (PI) Planning?

Options:

A.

Encourage discussion of each team's product Vision as part of the final plan re-view


B.

Verify that each team's uncommitted objectives have lower business value than the committed PI Objectives in order to reflect proper prioritization


C.

Facilitate the ROAMing of each team's risks


D.

Facilitate all teams when they are presenting their final plans to the entire Agile Release Train


Expert Solution