When looking at a program board at the end of program increment (Pl) planning, what does it mean when a feature is placed in a team's swim lane with no strings?


A.

That the feature can be completed by that team independently


B.

That the team has not broken the feature into stories yet and has not identified dependencies


C.

That it has dependencies on teams in other Agile release trains (ARTs) or Solution Trains


D.

That the team has been assigned, but the feature’ uépendencies have not been identified yet