The ART Sync event is a combination of PO-sync and Scrum of Scrums events. It is used to coordinate progress across the Agile Release Train, involving Scrum Masters/Team Coaches, Product Owners, and other select team members to discuss progress, impediments, scope, and priority adjustments.