Questions # 16:

Which of the following is an output of the Perform Integrated Change Control process?

Options:

A.

Project document updates


B.

Organizational process assets updates


C.

Change requests


D.

Deliverables


Expert Solution
Questions # 17:

Which is an input to the Verify Scope process?

Options:

A.

Performance report


B.

Work breakdown structure (WBS)


C.

Requested changes


D.

Project management plan


Expert Solution
Questions # 18:

The process of identifying the stakeholders' information needs is completed during:

Options:

A.

Plan Communications.


B.

Manage Stakeholder Expectations.


C.

Stakeholder Analysis.


D.

Identify Stakeholders.


Expert Solution
Questions # 19:

The purpose of inspection in Perform Quality Control is to keep errors:

Options:

A.

in line with a measured degree of conformity.


B.

out of the hands of the customer.


C.

in a specified range of acceptable results.


D.

out of the process.


Expert Solution
Questions # 20:

What is the most accurate rough order of magnitude (ROM)?

Options:

A.

In the Initiation phase, the estimate is in the range of +/- 50%.


B.

In the Planning phase, the estimate is in the range of +/- 50%.


C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.


D.

In the Closing phase, the estimate is in the range of +/- 15%.


Expert Solution
Questions # 21:

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

Options:

A.

Limited


B.

Low to moderate


C.

Moderate to high


D.

High to almost total


Expert Solution
Questions # 22:

Which process occurs within the Monitoring and Controlling Process Group?

Options:

A.

Control Costs


B.

Plan Quality


C.

Perform Quantitative Risk Analysis


D.

Determine Budget


Expert Solution
Questions # 23:

Which of the following is an output of Direct and Manage Project Execution?

Options:

A.

Project management plan


B.

Change request status updates


C.

Organizational process assets updates


D.

Work performance information


Expert Solution
Questions # 24:

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

Options:

A.

Cost-reimbursable contracts


B.

Time and Material contracts (T&M)


C.

Fixed-price contracts


D.

Cost Plus Fixed Fee Contracts (CPFF)


Expert Solution
Questions # 25:

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

Options:

A.

Requirements traceability matrix


B.

Work breakdown structure (WBS) dictionary


C.

Requirements management plan


D.

Requirements documentation


Expert Solution
Questions # 26:

Which of the following is a tool and technique used in the Develop Schedule process?

Options:

A.

Three-point estimates


B.

Resource leveling


C.

Precedence diagramming method


D.

Bottom-up estimating


Expert Solution
Questions # 27:

Which tool or technique is used in Close Procurements?

Options:

A.

Contract plan


B.

Procurement plan


C.

Closure process


D.

Procurement audits


Expert Solution
Questions # 28:

What is the primary benefit of meeting quality requirements?

Options:

A.

Quality metrics


B.

Less rework


C.

Quality control measurements


D.

Benchmarking


Expert Solution
Questions # 29:

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide


B.

The Standard for Program Management


C.

Organizational Project Management Maturity Model (OPM3$)


D.

Guide to the Project Management Body of Knowledge (PMBOK®)


Expert Solution
Questions # 30:

Which provides the basic framework for managing a project?

Options:

A.

Project life cycle


B.

Work breakdown structure (WBS)


C.

Enterprise environmental factors


D.

Project initiation