Question #: 24
Topic #: 3

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?


A.

Cost-reimbursable contracts


B.

Time and Material contracts (T&M)


C.

Fixed-price contracts


D.

Cost Plus Fixed Fee Contracts (CPFF)