Questions # 46:

One of the key benefits of the Plan Human Resource Management process is that it:

Options:

A.

outlines team selection guidelines and team member responsibilities.


B.

establishes project roles and responsibilities.


C.

improves teamwork, interpersonal skills, and competencies.


D.

provides an accurate appraisal of team member performance.


Expert Solution
Questions # 47:

Progressively elaborating high-level information into detailed plans is performed by the:

Options:

A.

project management office


B.

portfolio manager


C.

program manager


D.

project manager


Expert Solution
Questions # 48:

Through whom do project managers accomplish work?

Options:

A.

Consultants and stakeholders


B.

Stakeholders and functional managers


C.

Project team members and consultants


D.

Project team members and stakeholders


Expert Solution
Questions # 49:

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Options:

A.

Activity network diagrams


B.

Affinity diagrams


C.

Matrix diagrams


D.

Interrelationship digraphs


Expert Solution
Questions # 50:

A disadvantage associated with virtual teams is that they:

Options:

A.

Require communication technology that is not readily available.


B.

Create difficulties when including people with disabilities.


C.

Often cannot accommodate teams that work different hours or shifts.


D.

Create the possibility for misunderstandings to arise.


Expert Solution
Questions # 51:

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Options:

A.

Procurement documents


B.

Inspection and audits


C.

Estimate budget


D.

Risk register


Expert Solution
Questions # 52:

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

Options:

A.

Identify Risks


B.

Plan Risk Management


C.

Perform Qualitative Risk Analysis


D.

Perform Quantitative Risk Analysis


Expert Solution
Questions # 53:

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

Options:

A.

100


B.

120


C.

1,000


D.

1,200


Expert Solution
Questions # 54:

Which enterprise environmental factors may influence Plan Schedule Management?

Options:

A.

Cultural views regarding time schedules and professional and ethical behaviors


B.

Historical information and change control procedures


C.

Risk control procedures and the probability and impact matrix


D.

Resource availability and organizational culture and structure


Expert Solution
Questions # 55:

Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

Options:

A.

Define Activities


B.

Direct and Manage Project Work


C.

Develop Project Management Plan


D.

Develop Project Charter


Expert Solution
Questions # 56:

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs


B.

Control Costs


C.

Plan Cost Management


D.

Determine Budget


Expert Solution
Questions # 57:

In the Define Activities process, the schedule management plan is used to:

Options:

A.

Capture the lessons learned from other projects for comparison.


B.

Contain the standard activity list.


C.

Document and support the project change requests.


D.

Prescribe the level of detail needed to manage the work.


Expert Solution
Questions # 58:

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

Options:

A.

Acquire Project Team.


B.

Plan Human Resource Management.


C.

Manage Project Team.


D.

Develop Project Team.


Expert Solution
Questions # 59:

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

Options:

A.

Information management systems


B.

Work performance reports


C.

Stakeholder analysis


D.

Data gathering and representation


Expert Solution
Questions # 60:

The following is a network diagram for a project.

Question # 60

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I


B.

A-B-C-F-H-I


C.

A-D-E-F-G-I


D.

A-D-E-F-H-I


Expert Solution