Pass the PMI CAPM PMI-100 Questions and answers with CertsForce

Viewing page 10 out of 15 pages
Viewing questions 136-150 out of questions
Questions # 136:

Plan-do-check-act is also known as:

Options:

A.

prevention over inspection.


B.

statistical sampling.


C.

management responsibility,


D.

continuous improvement.


Expert Solution
Questions # 137:

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

Options:

A.

The risk of achieving the shortened project time is increased.


B.

The critical path will have positive total float.


C.

Contingency reserves are released for redeployment by the project manager.


D.

Duration buffers are added to maintain a focus on planned activity durations.


Expert Solution
Questions # 138:

Which of the following is a tool or technique used in the Determine Budget process?

Options:

A.

Variance analysis


B.

Three-point estimating


C.

Bottom-up estimating


D.

Historical relationships


Expert Solution
Questions # 139:

Which characteristics do effective project managers possess?

Options:

A.

Project management knowledge, performance skills, and personal effectiveness


B.

Preparedness, project management knowledge, and personality characteristics


C.

General management, preparedness, and project management knowledge


D.

Assertiveness, collaboration, and performance skills


Expert Solution
Questions # 140:

Which activity may occur at project or phase closure?

Options:

A.

Acceptance of deliverables


B.

Change requests


C.

Project management plan updates


D.

Benchmarking


Expert Solution
Questions # 141:

Which of the following is a strategy to deal with positive risks or opportunities?

Options:

A.

Mitigate


B.

Transfer


C.

Exploit


D.

Avoid


Expert Solution
Questions # 142:

Projects are separated into phases or subprojects; these phases include:

Options:

A.

feasibility study, concept development, design, and prototype.


B.

initiate, plan, execute, and monitor.


C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.


D.

Identify Stakeholders, develop concept, build, and test.


Expert Solution
Questions # 143:

Which of the following are three inputs to the risk register?

Options:

A.

Risk register updates, stakeholder register, and quality management plan


B.

Communication management plan, enterprise environmental factors, and activity duration estimates


C.

Risk management plan, activity cost estimates, and project documents


D.

Project scope statement, organizational process assets, and scope baseline


Expert Solution
Questions # 144:

Which input will be used when tasked with developing the human resource plan?

Options:

A.

Project management plan


B.

Activity resource requirements


C.

Resource calendar


D.

Project staff assignments


Expert Solution
Questions # 145:

At the end of the project, what will be the value of SV?

Options:

A.

Positive


B.

Zero


C.

Negative


D.

Greater than one


Expert Solution
Questions # 146:

Which is one of the determining factors used to calculate CPI?

Options:

A.

EV


B.

SPI


C.

PV


D.

ETC


Expert Solution
Questions # 147:

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

Options:

A.

Two


B.

Four


C.

Five


D.

Twelve


Expert Solution
Questions # 148:

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

Options:

A.

Schedule


B.

Quality


C.

Communications


D.

Cost


Expert Solution
Questions # 149:

The cost benefit analysis tool is used for creating:

Options:

A.

Pareto charts.


B.

quality metrics.


C.

change requests,


D.

Ishikawa diagrams.


Expert Solution
Questions # 150:

Activity cost estimates are quantitative assessments of the probable costs required to:

Options:

A.

Create WBS.


B.

complete project work.


C.

calculate costs.


D.

Develop Project Management Plan.


Expert Solution
Viewing page 10 out of 15 pages
Viewing questions 136-150 out of questions