PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 137 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 137 Topic 14 Discussion

PMI-100 Exam Topic 14 Question 137 Discussion:
Question #: 137
Topic #: 14

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?


A.

The risk of achieving the shortened project time is increased.


B.

The critical path will have positive total float.


C.

Contingency reserves are released for redeployment by the project manager.


D.

Duration buffers are added to maintain a focus on planned activity durations.


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.