Pass the PMI CAPM PMI-100 Questions and answers with CertsForce

Viewing page 12 out of 15 pages
Viewing questions 166-180 out of questions
Questions # 166:

The diagram below is an example of a:

Question # 166

Options:

A.

Risk breakdown structure (RBS).


B.

Project team.


C.

SWOT Analysis.


D.

Work breakdown structure (WBS).


Expert Solution
Questions # 167:

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

Options:

A.

Control Scope


B.

Collect Requirements


C.

Create WBS


D.

Define Scope


Expert Solution
Questions # 168:

Which of the following is a project constraint?

Options:

A.

Twenty-five percent staff turnover is expected.


B.

The technology to be used is cutting-edge.


C.

Project leadership may change due to volatile political environment.


D.

The product is needed in 250 days.


Expert Solution
Questions # 169:

Expected monetary value (EMV) is computed by which equation?

Options:

A.

Value of each possible outcome multiplied by probability of occurrence


B.

Value of each possible outcome multiplied by probability of non-occurrence


C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together


D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together


Expert Solution
Questions # 170:

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Options:

A.

Cost Plus Fixed Fee Contract (CPFF)


B.

Cost Plus Incentive Fee Contract (CPIF)


C.

Firm Fixed Price Contract (FFP)


D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)


Expert Solution
Questions # 171:

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

Options:

A.

Manage Stakeholder Expectations.


B.

Monitor and Control Risks.


C.

Plan Risk Management.


D.

Report Performance.


Expert Solution
Questions # 172:

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

Options:

A.

operate separately.


B.

move together in batches,


C.

overlap and interact.


D.

move in a sequence.


Expert Solution
Questions # 173:

Which tools or techniques will a project manager use for Develop Project Team?

Options:

A.

Negotiation


B.

Roles and responsibilities


C.

Recognition and rewards


D.

Prizing and promoting


Expert Solution
Questions # 174:

Who selects the appropriate processes for a project?

Options:

A.

Project stakeholders


B.

Project sponsor and project stakeholder


C.

Project manager and project team


D.

Project manager and project sponsor


Expert Solution
Questions # 175:

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

Options:

A.

Control chart


B.

Earned value


C.

Variance


D.

Trend


Expert Solution
Questions # 176:

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

Options:

A.

Historical information and the lessons-learned database.


B.

Historical information and the stakeholder register.


C.

Organizational process assets and the lessons-learned database.


D.

Project documents and historical information.


Expert Solution
Questions # 177:

Which of the following statements correctly characterizes pull communication?

Options:

A.

It includes letters, memos, reports, emails, and faxes.


B.

It requires recipients to access communication content at their own discretion.


C.

It is the most efficient way to ensure a common understanding among all participants.


D.

It is primarily used when the volume of information to be transferred is minimal.


Expert Solution
Questions # 178:

What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?

Options:

A.

Organizational process assets


B.

Enterprise environmental factors


C.

Project management processes


D.

Project scope management plan


Expert Solution
Questions # 179:

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Estimate Costs


B.

Estimate Activity Resources


C.

Control Costs


D.

Determine Budget


Expert Solution
Questions # 180:

The Verify Scope process is primarily concerned with:

Options:

A.

formalizing acceptance of the completed project deliverables.


B.

accuracy of the work deliverables.


C.

formalizing approval of the scope statement.


D.

accuracy of the work breakdown structure (WBS).


Expert Solution
Viewing page 12 out of 15 pages
Viewing questions 166-180 out of questions