PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 172 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 172 Topic 18 Discussion

PMI-100 Exam Topic 18 Question 172 Discussion:
Question #: 172
Topic #: 18

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:


A.

operate separately.


B.

move together in batches,


C.

overlap and interact.


D.

move in a sequence.


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.