Pass the PMI CAPM PMI-100 Questions and answers with CertsForce

Viewing page 11 out of 15 pages
Viewing questions 151-165 out of questions
Questions # 151:

The correct equation for schedule variance (SV) is earned value:

Options:

A.

minus planned value [EV - PV].


B.

minus actual cost [EV - AC].


C.

divided by planned value [EV/PV],


D.

divided by actual cost [EV/AC].


Expert Solution
Questions # 152:

What are the identified risks for doing excessive decomposition in a WBS?

Options:

A.

Insufficient project funding and disqualification of sellers


B.

Insufficient project funding and ineffective use of resources


C.

Disqualification of sellers and non-productive management efforts


D.

Non-productive management effort and inefficient use of resources


Expert Solution
Questions # 153:

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).


B.

Cost Plus Fixed Fee Contract (CPFF).


C.

Fixed Price Incentive Fee Contract (FPIF).


D.

Time and Material Contract (T&M).


Expert Solution
Questions # 154:

Which of the following is a tool and technique used to monitor risk?

Options:

A.

Technical performance measurement


B.

Cost performance baseline


C.

Benchmarking


D.

Cost of quality


Expert Solution
Questions # 155:

A tool and technique used during the Collect Requirements process is:

Options:

A.

prototypes.


B.

expert judgment.


C.

alternatives identification.


D.

product analysis.


Expert Solution
Questions # 156:

Inputs to the Plan Risk Management process include the:

Options:

A.

cost management plan.


B.

risk management plan,


C.

activity list,


D.

risk register.


Expert Solution
Questions # 157:

Which of the following is an input to the Develop Project Charter process?

Options:

A.

Work performance information


B.

Project management plan


C.

Business case


D.

Change requests


Expert Solution
Questions # 158:

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

Options:

A.

Work performance reports


B.

Assumptions logs


C.

Network diagrams


D.

Academic studies


Expert Solution
Questions # 159:

Which of the following is a tool or technique used in the Acquire Project Team process?

Options:

A.

Networking


B.

Training


C.

Negotiation


D.

Issue log


Expert Solution
Questions # 160:

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Options:

A.

Initiating


B.

Planning


C.

Executing


D.

Closing


Expert Solution
Questions # 161:

Which of the following is an output of the Conduct Procurements process?

Options:

A.

Project statement of work


B.

Selected sellers


C.

Risk register updates


D.

Teaming agreements


Expert Solution
Questions # 162:

After Define Activities and Sequence Activities, the next process is:

Options:

A.

Estimate Activity Resources.


B.

Estimate Activity Durations,


C.

Develop Schedule.


D.

Control Schedule.


Expert Solution
Questions # 163:

Prototype development may be used as a tool for which of the following risk response strategies?

Options:

A.

Avoid


B.

Accept


C.

Mitigate


D.

Exploit


Expert Solution
Questions # 164:

Which quality control technique illustrates the 80/20 principle?

Options:

A.

Ishikawa diagram


B.

Control chart


C.

Run chart


D.

Pareto chart


Expert Solution
Questions # 165:

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

Options:

A.

Acquisition


B.

Negotiation


C.

Virtual team


D.

Pre-assignment


Expert Solution
Viewing page 11 out of 15 pages
Viewing questions 151-165 out of questions