PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 180 Topic 19 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 180 Topic 19 Discussion

PMI-100 Exam Topic 19 Question 180 Discussion:
Question #: 180
Topic #: 19

The Verify Scope process is primarily concerned with:


A.

formalizing acceptance of the completed project deliverables.


B.

accuracy of the work deliverables.


C.

formalizing approval of the scope statement.


D.

accuracy of the work breakdown structure (WBS).


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.