Question #: 60
Topic #: 7

The following is a network diagram for a project.

PMI-100 Question 60

What is the critical path for the project?


A.

A-B-C-F-G-I


B.

A-B-C-F-H-I


C.

A-D-E-F-G-I


D.

A-D-E-F-H-I