PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 26 Topic 3 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 26 Topic 3 Discussion

PMI-100 Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

Which of the following is a tool and technique used in the Develop Schedule process?


A.

Three-point estimates


B.

Resource leveling


C.

Precedence diagramming method


D.

Bottom-up estimating


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.