PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 17 Topic 2 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 17 Topic 2 Discussion

PMI-100 Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

Which is an input to the Verify Scope process?


A.

Performance report


B.

Work breakdown structure (WBS)


C.

Requested changes


D.

Project management plan


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.