The work breakdown structure:
You are project manager and working on gathering requirements and estimating for the project. Which process group are you in?
You are the project manager for a new construction project in your city. Your personal friend is bidding on the project. Your friend has asked you to give them an indication of the budget for this project so that they do not overbid and lose the deal. What is the most appropriate response?
With respect to earned value analysis, which of the following is the value of work actually completed?
You are project manager of a project. A customer requests a scope change in the project . In order to determine the impact of the requested change, you will need a work breakdown structure, change request, scope management plan, and:
Planning components are tools or techniques of the Define Activities process. Which of the following are planning components?
Which of the following are not essential for project close out ?
To determine the impact of a change that has occurred, which of the following should be taken?
As a project manager, you are responsible for maintaining and ensuring integrity for all of the following except:
Bar charts generally illustrate:
How many communication channels will be required in a project having five individual participants?
Which of the following is true regarding IRR?
Control Costs includes all of the following EXCEPT:
18 You are the project manager of a software company. As software development can be very chaotic, your company has decided to follow a more rigorous approach to software development. Specifically your company has chosen to adopt the extreme programming XP methodology for your current software project. The XP methodology is highly iterative, and produces numerous deliverables include UML diagrams, architecture diagrams, prototypes and test-cases. Assume you are in the Sequence Activities phase of the project. Which of the following sequencing methods should you use to identify the logical relationships between tasks, so that the activities can be sequenced correctly?
Which of the following conflict resolution approaches is likely to lead to the MOST long-lasting solutions?