Questions # 211:

As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following?

Options:

A.

Documenting and meeting the requirements


B.

Reporting project status regularly and in a timely manner


C.

Documenting and meeting the performance measurements


D.

Reporting changes and updating the project plan and other project documents where appropriate


Expert Solution
Questions # 212:

As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following?

Options:

A.

Documenting and meeting the requirements


B.

Reporting project status regularly and in a timely manner


C.

Documenting and meeting the performance measurements


D.

Reporting changes and updating the project plan and other project documents where appropriate


Expert Solution
Questions # 213:

Fast tracking involves:

Options:

A.

Developing workarounds for previous problems.


B.

An increase in project risk.


C.

Getting people to work longer with overtime.


D.

Meeting schedule objectives by adding resources.


Expert Solution
Questions # 214:

Duration estimates indicate:

Options:

A.

How many work periods an activity is expected to last.


B.

How many hours a resource will work on an activity.


C.

When an activity is likely to finish.


D.

When an activity is likely to start.


Expert Solution
Questions # 215:

Which is not true about change requests :

Options:

A.

They always require additional funding.


B.

They happen while the project work is being done.


C.

They can be written or verbal.


D.

They can be requested by a stakeholder.