Questions # 166:

Percent complete is calculated by ___________.

Options:

A.

ACWP/BAC


B.

BCWP-ACWP


C.

BCWP/BAC


D.

EAC/BAC


Expert Solution
Questions # 167:

AON refers to __________.

Options:

A.

Precedence Diagramming Method [PDM]


B.

Arrow Diagramming Method [ADM]


C.

Fragment Network


D.

All of the above


Expert Solution
Questions # 168:

A mandatory prerequisite for team building is ___________.

Options:

A.

Funding for staff development activities


B.

Shared work ethics among team members


C.

Commitment from top level management


D.

Removal of troublesome individuals


Expert Solution
Questions # 169:

Risks are accepted when ___________.

Options:

A.

You develop a contingency plan to execute should the risk event occur


B.

You accept the consequences of the risk


C.

You transfer the risk to another party


D.

Both A and B


Expert Solution
Questions # 170:

Which of the following statements concerning bottom-up estimating is true?

Options:

A.

The cost and accuracy of bottom-up estimating is driven by the size of the individual work items.


B.

Smaller work items increase both cost and accuracy.


C.

Larger work items increase both cost and accuracy.


D.

Both A and B are true


Expert Solution
Questions # 171:

Mathematical models using linear, dynamic, integer, or algorithm models are considered _____________.

Options:

A.

Project selection methods


B.

Project selection criteria


C.

A form of expert judgment


D.

A form of historical information


Expert Solution
Questions # 172:

Which of the following is true regarding the NPV?

Options:

A.

NPV assumes reinvestment at the cost of capital.


B.

NPV assumes reinvestment at the prevailing rate.


C.

NPV assumes reinvestment at the NPV rate.


D.

NPV decisions should be made based on the highest value for all the selections.


Expert Solution
Questions # 173:

The party that needs the change resulting from the project, and who will be its custodian on completion is the _________.

Options:

A.

Owner


B.

client


C.

Sponsor


D.

Customer


Expert Solution
Questions # 174:

Which of the following is true about a project charter?

Options:

A.

A project charter should be published under the name of a manager external to the project.


B.

A project charter should be published under the project sponsor's name.


C.

A project charter should be published under the name of the project manager.


D.

A project charter should be published under the name of the project champion.


Expert Solution
Questions # 175:

Which characteristic distinguishes the network diagram from the Gant chart?

Options:

A.

Critical dependencies


B.

Few resources


C.

Critical dates


D.

key milestones


Expert Solution
Questions # 176:

What is one of the advantages of a functional organization?

Options:

A.

All employees report to two or more managers


B.

The organization is focused on projects.


C.

Teams are co located.


D.

All employees report to one manager and have a clear chain of command.


Expert Solution
Questions # 177:

Mathematical models using linear, dynamic, integer, or algorithm models are considered

Options:

A.

Project selection methods


B.

Project selection criteria


C.

A form of expert judgment


D.

A form of historical information


Expert Solution
Questions # 178:

___________ is a group of processes required to purchase or acquire products, services, or results needed outside the project team to perform the work.

Options:

A.

Procurement Management


B.

Planning Management


C.

Scope Management


D.

Control Management


Expert Solution
Questions # 179:

You are the project manager of a large construction project. The project objective is to construct a set of buildings in the city within 18 months from the project start date. Resources are not readily available because they are currently assigned to other projects. Nick, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Nick assigned to your project?

Options:

A.

Negotiation and influencing skills


B.

Communication and organizational skills


C.

Problem solving skills


D.

Communication skills


Expert Solution
Questions # 180:

You are the project manager and at the completion of the project, you MUST:

Options:

A.

Celebrate success with the team.


B.

Evaluate team member performance.


C.

get a sign-off from the customer.


D.

Plan a turnover meeting.


Expert Solution