PMI-002 Exam Topic 22 Question 215 Discussion:
Question #: 215
Topic #: 22

Which is not true about change requests :


A.

They always require additional funding.


B.

They happen while the project work is being done.


C.

They can be written or verbal.


D.

They can be requested by a stakeholder.