PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 184 Topic 19 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 184 Topic 19 Discussion

PMI-002 Exam Topic 19 Question 184 Discussion:
Question #: 184
Topic #: 19

With respect to earned value analysis, which of the following is the value of work actually completed?


A.

Actual Cost (AC)


B.

planed Value (PV)


C.

Cost Variance (CV)


D.

Earned Value (EV)


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.