PMI-002 Exam Topic 19 Question 182 Discussion:
Question #: 182
Topic #: 19

You are project manager and working on gathering requirements and estimating for the project. Which process group are you in?


A.

Planning


B.

Monitoring and Controlling


C.

Executing


D.

Initiating


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.