Holly is the project manager of a project in a functional environment. Jason, the functional manager, has just informed Holly a new requirement that he has approved for the project. Holly documents the change and updates the project scope. What document should Holly also update in light of this change?
You work as the project manager for Bluewell Inc. You are working on NGQQ Project for your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?
Which of the following processes is described in the statement below?
"It is the process of identifying the specific actions to be performed to produce the project deliverables."
Which of the following quality costs determines, assesses, or audits products or services to assure conformance to quality standards and performance requirements?
Fill in the blank with the appropriate term.
______ (also called contractor conferences, vendor conferences, and pre-bid conferences) are meetings with prospective sellers prior to preparation of a bid or proposal.
You work as a project manager for PassGuide Inc. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the ownership of the response?
You work as a project manager for PassGuide Inc. You are performing a task to generate a hierarchical list of resources related by function and resource type that is used to facilitate planning and controlling of project work. Which of the following components of project management will you use to accomplish the above task?
Which of the following components of EVA is described in the statement below?
"It is a measure of how much of the project value has been earned so far through completed work, that is, the budgeted cost of the work that has been performed through the project status date."
You work as a project manager for PassGuide Inc. You have to measure the potential risks on the two dimensions of a graph. Which of the following charts will you use to accomplish the task?
You are the project manager for your organization and would like to use a time and materials contract for a small project. What must a time and materials contract have to safeguard the project?