Question #: 19
Topic #: 2

You work as a project manager for PassGuide Inc. You have to measure the potential risks on the two dimensions of a graph. Which of the following charts will you use to accomplish the task?


A.

Gantt chart


B.

Risk probability and impact matrix


C.

Pareto chart


D.

Control chart