GIAC Certified Project Manager Certification Practice Test GCPM Question # 19 Topic 2 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 19 Topic 2 Discussion

GCPM Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

You work as a project manager for PassGuide Inc. You have to measure the potential risks on the two dimensions of a graph. Which of the following charts will you use to accomplish the task?


A.

Gantt chart


B.

Risk probability and impact matrix


C.

Pareto chart


D.

Control chart


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.