Question #: 20
Topic #: 3

You are the project manager for your organization and would like to use a time and materials contract for a small project. What must a time and materials contract have to safeguard the project?


A.

Terms for payment


B.

Approval from the project sponsor


C.

An approved vendor by a leading trade organization


D.

A not-to-exceed clause