Questions # 91:

Fill in the blank with the appropriate term.

A _______ is a scale of values for the vendors where not all of the values are of the same weight


Expert Solution
Questions # 92:

Which of the following is NOT an output of the Control Scope process?

Options:

A.

Project document updates


B.

Work performance measurements


C.

Accepted deliverables


D.

Change requests


Expert Solution
Questions # 93:

Which of the following components of EVA defines the total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity?

Options:

A.

PV


B.

AC


C.

CV


D.

EV


Expert Solution
Questions # 94:

Which of the following is described in the statement below?

"It measures the quality objectives of the project. It provides the foundation for measuring and reporting quality performance as part of the performance measurement baseline."

Options:

A.

Cost baseline


B.

Scope baseline


C.

Schedule baseline


D.

Quality baseline


Expert Solution
Questions # 95:

Which of the following processes records the results of executing quality activities?

Options:

A.

Control risk


B.

Monitor risk


C.

Perform quality control


D.

Identify risk


Expert Solution
Questions # 96:

Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?

Options:

A.

Risk management plan


B.

Risk response plan


C.

Project sponsor


D.

Look-up table


Expert Solution
Questions # 97:

You are the project manager of TRT project. During execution phase of your project, Rick, a team member, complains that other team members are isolating him and this isolation is bothering him.

Which of the following is not a recommended step in order to resolve the issue?

Options:

A.

Apply team building measures to improve the team's effectiveness.


B.

Get more feed back from Rick.


C.

Get feedback on Rick from other team members.


D.

Shift Rick to another project.


Expert Solution
Questions # 98:

Which of the following processes is used to obtain formal acceptance of the project scope by the stakeholders?

Options:

A.

Expert judgment


B.

Identify risk


C.

Quality control


D.

Verify scope


Expert Solution
Questions # 99:

Which of the following is built by aggregating the costs of the individual work elements and then joining them at time intervals where meaningful actual cost information will be available?

Options:

A.

Cost baseline


B.

Cost estimation


C.

Cost controlling


D.

Cost budgeting


Expert Solution
Questions # 100:

Which of the following is the method used to convey a message?

Options:

A.

Sender


B.

Noise


C.

Receiver


D.

Medium


Expert Solution