Questions # 111:

Which of the following is a document that covers the work that will be done, how the work will be compensated, and any penalties for noncompliance?

Options:

A.

Project description


B.

Control chart


C.

Cost baseline


D.

Contract


Expert Solution
Questions # 112:

You are a new Project Manager that has been entrusted with a project to develop a machine which produces auto components. You have put together your project team and have begun executing your project. Recently, a conflict arose between two of your team members about a feature that will be incorporated in the design of the machine. Which of the following is the MOST APPROPRIATE technique to resolve this conflict?

Options:

A.

Compromising


B.

Collaborating


C.

Forcing


D.

Withdrawing


Expert Solution
Questions # 113:

You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?

Options:

A.

Contract Types


B.

Make-or-Buy Analysis


C.

Procurement Negotiations


D.

Expert Judgment


Expert Solution
Questions # 114:

Which of the following describes the statement below?

"It allocates continuous monitoring of the schedule, permits the project manager to track the critical activities, and alerts the project manager to the possibility that non-critical activities may be delayed beyond their total float, thus creating a new critical path and delaying project completion."

Options:

A.

CPM


B.

RBS


C.

Gantt chart


D.

WBS


Expert Solution
Questions # 115:

You are the project manager of the GHY Project for your functional organization. Another project manager that uses some of your project resources has asked that you allow the resources you both share to always be available for her project on every Thursday. The only conflict you have with this request that on Thursday mornings you have a regularly scheduled status meeting. You agree to the request and decide to move the status meeting to Tuesday morning going forward in your project.

What project plan must you update to reflect this change?

Options:

A.

Human Resources Management Plan


B.

Scope Management Plan


C.

Communications Management Plan


D.

Staffing Management Plan


Expert Solution
Questions # 116:

You work as a project manager for PassGuide Inc. You report the project details directly to the vice president and the administrator of your organization. In which of the following types of organization structures are you working?

Options:

A.

Jury


B.

Functional


C.

Projectized


D.

Matrix


Expert Solution
Questions # 117:

Which of the following statements describes the critical path?

Options:

A.

It is the shortest path in the project network diagram.


B.

It cannot be crashed.


C.

It is always one path with the longest duration.


D.

It shows the project's earliest date for completion.


Expert Solution
Questions # 118:

Amy works as a project manager for PassGuide Inc. She wants to determine those risks that may affect the project. Which of the following processes should Amy use to accomplish the task?

Options:

A.

Perform qualitative risk analysis


B.

Plan risk responses


C.

Perform quantitative risk analysis


D.

Identify risk


Expert Solution
Questions # 119:

You work as a project manager for PassGuide Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?

Options:

A.

0.87


B.

0.80


C.

0.86


D.

0.84


Expert Solution