You are the project manager of the GHY Project for your functional organization. Another project manager that uses some of your project resources has asked that you allow the resources you both share to always be available for her project on every Thursday. The only conflict you have with this request that on Thursday mornings you have a regularly scheduled status meeting. You agree to the request and decide to move the status meeting to Tuesday morning going forward in your project.
What project plan must you update to reflect this change?