GCPM Exam Topic 12 Question 114 Discussion:
Question #: 114
Topic #: 12

Which of the following describes the statement below?

"It allocates continuous monitoring of the schedule, permits the project manager to track the critical activities, and alerts the project manager to the possibility that non-critical activities may be delayed beyond their total float, thus creating a new critical path and delaying project completion."


A.

CPM


B.

RBS


C.

Gantt chart


D.

WBS