Questions # 71:

You have been assigned as the Project Manager for a new project that involves development of a new interface for your existing time management system. You know that developers are available in your organization, and would like to use them. However, your program manager thinks that an outside company needs to be engaged to complete this development. Which of the following will help you to convince your project manager to use the internal resources?

Options:

A.

Expert Judgment


B.

Make or buy analysis


C.

Survey Questionnaire


D.

Issue log


Expert Solution
Questions # 72:

Which of the following are the types of casual/econometric forecasting methods?

Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

ARIMA


B.

Econometrics


C.

ARMA


D.

Scenario building


Expert Solution
Questions # 73:

What component of the change control process examines the entire project to determine the proposed change's impact on the project scope, time, cost, quality, human resources, communications, risk, and procurement?

Options:

A.

Integrated change control


B.

Scope change control system


C.

Configuration management


D.

Project management information management system


Expert Solution
Questions # 74:

Identify Risks is the process of determining which risks may affect the project. Which of the following are inputs of the Identify risks process?

Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Risk register


B.

Scope baseline


C.

Project documents


D.

Risk management plan


Expert Solution
Questions # 75:

Which of the following is described in the statement below?

"It is defined as the work element that must be carefully monitored, documented, and managed to make the success of an organization, program, or project."

Options:

A.

Red rated activity


B.

High alert activity


C.

Action items


D.

Critical activity


Expert Solution
Questions # 76:

You are the project manager of the UTN Project and are working on the roles and responsibilities for your project. You'll need to define four aspects of the roles and responsibilities. All of the following must be defined except for which one?

Options:

A.

Management


B.

Competency


C.

Role


D.

Responsibilities


Expert Solution
Questions # 77:

You work as a project manager for PassGuide Inc. You have to determine the seller for the project. You have received proposals from five vendors and they are all very good proposals, and the value is worth the same. You have to build a method of ranking each vendor. You have allocated 35 points to experience and 15 points for all the other categories to judge the vendors. Which of the following types of source selection process is used in the above scenario?

Options:

A.

Screening system


B.

Benefits-cost analysis


C.

Weighting system


D.

Seller rating system


Expert Solution
Questions # 78:

You work as a project manager for PassGuide Inc. You have to work on an agreement that creates and defines obligations between two or more parties. Which of the following types of agreement will you work on?

Options:

A.

Service level agreement


B.

NDA


C.

Statement of work


D.

Contract


Expert Solution
Questions # 79:

In which of the following processes are the results of executing the quality activities recorded and monitored in order to assess performance and recommend necessary changes?

Options:

A.

Perform Quality Control


B.

Plan Quality


C.

Control Cost


D.

Perform Quality Assurance


Expert Solution
Questions # 80:

Kelly is the project manager of her organization. She is reviewing the project network diagram to confirm that the resource she has identified is available to complete the project assignments without conflicting with other activities in the project node. The availability of resources will help Kelly determine the final finish date for the project. What scheduling technique is Kelly using?

Options:

A.

Critical Path method


B.

Critical Chain method


C.

Resource utilization


D.

Resource leveling heuristics


Expert Solution