Question #: 74
Topic #: 8

Identify Risks is the process of determining which risks may affect the project. Which of the following are inputs of the Identify risks process?

Each correct answer represents a complete solution. Choose all that apply.


A.

Risk register


B.

Scope baseline


C.

Project documents


D.

Risk management plan


Get Premium GCPM Questions