Kelly is the project manager of her organization. She is reviewing the project network diagram to confirm that the resource she has identified is available to complete the project assignments without conflicting with other activities in the project node. The availability of resources will help Kelly determine the final finish date for the project. What scheduling technique is Kelly using?


A.

Critical Path method


B.

Critical Chain method


C.

Resource utilization


D.

Resource leveling heuristics