You work as a project manager for PassGuide Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?


A.

0.87


B.

0.80


C.

0.86


D.

0.84